Больше информации по резюме будет доступно после регистрации
ЗарегистрироватьсяWas more than two weeks ago
Female, 40 years, born on 18 December 1985
Uralsk, willing to relocate, prepared for business trips
Piping / Pipeline Engineer
Specializations:
- Other
Employment type: full time, project work/one-time assignment
Work experience 18 years 5 months
May 2018 — currently
8 years
KazGiproNefteTrans (KGNT)
Uralsk, www.kgnt.kz
Oil and Gas... Show more
Piping / Pipeline Engineer
As Piping Engineer is responsible for develop drawings of piping systems in accordance with the design specifications, scope of works, design parameters, rules, company procedures and practices of the production’s work. Review and provide comments on the design drawings of other departments, contractors. Present reports on the status of documentation and on the progress of work. Review of the technical documentation and detailed drawings of other departments. Preparation of Work Pack (piping general arrangement, isometric, detail drawings, MTO, Tie-in schedule, closing site queries). Site survey: identify tie-in point of new pipes according to P&ID from client; Ensure that all aspects of the project design comply with standards SNiP, GOST, ASME, API, ASTM, NACE etc., safety requirements and procedures. Perform “As-Built” drawings of the existing piping systems according to procedures.
Responding to Technical Queries and Site Queries during design and construction phases.
As Pipeline Engineer is responsible for preparation of Construction Work Pack as per RoK Codes and International Standards (scope of work, pipeline and route layout, alignment sheets, detail crossing drawings, crossing matrix, bill of quantity, MTO, Tie-in schedule, route selection report and response for site queries). Site survey: visual review of pipeline right of way in the field as per RoK Codes and International Standards. Engineering support of procurement and construction. Review of Pipeline Mechanical Stress report, Topo and Geo Reports.
August 2017 — May 2018
10 months
Aktau, www.maerskoil.com
Chemical Production, Fertilizers... Show more
Piping Engineer
Response to Technical Queries and Site Queries during design and construction phases. Responsible for technical evaluation of vendor quotations / tender proposals on piping materials. Support on preparation of technical parts of tender documents, as well as in technical pre-qualification of the Bidders, review of technical bids for compliance with initial requirements and relevant Company, local and international standards. Engineering support to the projects for existing plant modifications and new constructed facilities. Prepare the scope of works for design activities for facility modification projects. Control and support design contractors for piping / mechanical deliverables during FEED and detail design phases, i.e. discipline quality control as well as multidisciplinary interface check of design deliverables. Technical support to Projects, Operations, Maintenance and with piping engineering expertise. Site survey: identify tie-in point of new pipes according to P&ID. Assist piping and material Technical Authorities as well as for preparation of deviation requests when deviating from Maersk Oil Technical standards requirements. Review the documentation of engineering contractors against Company specifications and ensure conformity of those to Maersk Standards/Specifications, local Kazakh standards (SNiP and GOST) and International standards (API / ASME / ISO (EN), DIN).
October 2015 — August 2017
1 year 11 months
KPO B.V.
Aksay (Kazakhstan), www.kpo.kz
Piping Engineer
Response for develop, review of projects and drawings of piping systems in accordance with the design specifications, scope of works, design parameters, rules, company procedures and practices of the production’s work. Consider, perform analysis of the proposed equipment and materials by vendors for compliance with company procedures and project materials and report to Lead Engineer. Review project specifications, design instructions, P&ID’s and information about vendors. Develop drawings piping specifications, standard drawings, design instructions, general plans, P&ID’s and information about vendors. Share information and interact with the designers and engineers from the other project disciplines. Review and provide comments on the design drawings of other departments, contractors. Present reports on the status of documentation and on the progress of work. Review of the technical documentation and detailed drawings. Preparation of Work Pack (piping general arrangement, isometric, detail drawings, MTO, Tie-in schedule, closing site queries). Site survey: identify tie-in point of new pipes according to P&ID; Ensure that all aspects of the project design comply with standards SNiP, GOST, ASME, API, ASTM, NACE etc., safety requirements and procedures. Perform “As-Built” drawings of the existing piping systems according to procedures.
March 2015 — August 2015
6 months
WoodGroup PSN
Atyrau
Piping Designer
Response for design related to piping systems of Tengiz field; preparation of piping general arrangement, isometric, detail drawings, MTO, Tie-in schedule. Develop plot plan, general arrangement. Site survey: identify tie-in point of new pipes according to P&ID; select optimal routing of new piping. Create drawing register and review drawings, data sheets of over discipline (civil, instrument, mechanical); check drawings (plot plan, general arrangement, isometric, MTO, material requisition). Ensure that all aspects of the project design comply with standards SNiP, GOST, VSN, ASME, API, ASTM, NACE etc., safety and client requirements and procedures. Perform “As-Built” of installed piping systems according to procedures.
July 2013 — December 2014
1 year 6 months
LLP "Asia Global Service"
Uralsk
Piping Engineer
• Preparation of technical documentation for construction;
• Modification of working drawings of the project;
• Performed As-Built on work drawings and registered them on company’s database;
• Filled, registered on database and checked Punch List for hydrotest and construction;
• Performed measurements for the drawing’s modification and registered;
• Performed of drawings in accordance with SNiP and procedures of Client;
• Performed of drawings using AutoCAD 2014 (2D/3D) program;
August 2012 — July 2013
1 year
QED International
Atyrau
ACS (database) Administrator
• Preparing DAC’s (Document Acceptance Certificate) for closed sub-systems;
• Completing of final documents;
• Receiving the documents from contractors;
• Register of documents on company’s database;
• Find in IMIS (Integrated Management Information System) System Limit Drawings & Engineering Drawings for DAC’s;
• Preparing dossiers and dispatching them to onshore (Mechanical completion. Pre-commissioning and ICAT class ITRs);
• Register the documents (Punch List, ITR (Inspections Test Records), Check list) and uploading the scanned version in ACS (Automated Completion System);
• Reviewing and advising contractors with the conformance of company standards and procedures;
• Provide on daily bases reports of closed quantity of documents;
June 2011 — August 2012
1 year 3 months
QED International
Atyrau
Final Dossier Technician
• Receiving the documents from contractors;
• Register of documents on company’s database;
• Completing of final documents;
• Register the documents (Punch List, ITR (Inspections Test Records), Check list) and uploading the scanned version in ACS (Automated Completion System);
• Reviewing and advising contractors with the conformance of company standards and procedures;
• Work with IMIS (Integrated Management Information System);
• Provide on daily bases reports of closed quantity of documents;
• Preparing dossiers and dispatching them to onshore (Mechanical completion. Pre-commissioning and ICAT class ITRs);
February 2010 — February 2011
1 year 1 month
Bonatti S.p.A.
Aksay (Kazakhstan), www.bonattinternational.com
Piping Engineer
• Preparation of technical documentation for construction;
• Modification of working drawings of the project;
• Development of plan of work for lifting cranes from 45tons to 250tons;
• Performed As-Built on work drawings and registered them on company’s database;
• Calculated a lifting capacity of cranes and performed schemes for work permit;
• Filled, registered on database and checked Punch List for hydrotest and construction;
• Performed measurements for the drawing’s modification and registered;
December 2008 — February 2010
1 year 3 months
Tecnomare S.p.A.
Aksay (Kazakhstan), www.tecnomareservice.it
Land Surveyor Engineer
• Responsible for preparation of “Recultivation of lands during construction” project;
• Performed a plot plan for pipeline from well to manifold and for cable from well to transformer substation;
• Performed calculation for removal and return back of humus on the basis of the geological and geodesic report of the well;
• Performed drawings using AutoCAD program;
• Prepared an explanatory note for project;
• To give a report to head of department and to client regarding the status of the project;
• Performed a project for recultivation of land damaged during construction in accordance with SNiP and Company procedures;
• For six months was pointed as an ecologist-engineer;
• Performed an environmental part of the explanatory note according to the methodology;
• Worked on software package ERA
January 2008 — December 2008
1 year
Tecnomare S.p.A.
Aksay (Kazakhstan), www.tecnomareservice.it
CAD Operator
• Performance of drawings using AutoCAD program;
• To assist engineers in projects;
• Preparation of work drawings of projects in accordance with the procedures of the Company and Clients;
June 2007 — January 2008
8 months
JSC “Aksaigasservice”
Aksay (Kazakhstan), www.ags.kz
Structural / Design Engineer
• Responsible for design of platform for service equipment (metal structural) on the field;
• Participation in designing of warehouse, fire station and industrial building
• Preparation of scope of work and design structural steelwork and foundation, concrete slab, road crossing, pipe supports, walkways
• Performance of drawings in accordance with SNiP / GOST and procedures of Client;
• To give a report to head of department regarding the status of the project;
Skills
Skill proficiency levels
Driving experience
Driver's license category B
Higher education
2008
Higher education
West Kazakhstan Agrarian – Technical University named Zhangir khan
Engineering protection of the environment, Engineer
Languages
Professional development, courses
2021
Training Center
KPO B.V., H2S Certificate
2013
Authorized Training Centre of Autodesk
Server Plus, Certificate of AutoCAD 2014 2D/3D-Modeling
2013
Training Center
The Planet of Leaders, The program of Leadership
2009
Training Center
Atana service, English Courses, Intermediate level
2009
Training Center
NordEcoConsult, Professional development in work on software package “ERA”
2008
West Kazakhstan Agrarian – Technical University, named Zhangir khan
Polytechnic Faculty, Certificate of Management and Control of Land Recultivation Projects
Citizenship, travel time to work
Citizenship: Kazakhstan
Permission to work: Kazakhstan
Desired travel time to work: Doesn't matter